Frisco · Collin & Denton counties
(945) 455-4412CallGet an Estimate

Learn

How do you clear land in North Texas?

The land clearing process from first walk to finished ground: which method fits your end use, what North Texas brush does after it is cut, and the city, county and state rules that shape the job.

Updated · Homestead Land Clearing

You clear land in North Texas by deciding the end use first, then choosing the method that leaves the right things in the ground: mulching for pasture and trails, clearing and grubbing for anything that will carry a slab or pavement. Check tree permits, burn rules, creeks and utilities for that address before any machine starts. This guide from Homestead Land Clearing walks through each decision.

What land clearing is, and what each method leaves in the ground

Land clearing is the removal of trees, brush and surface vegetation from a defined area so the ground can be used for something else. The word covers several distinct jobs, and the difference is mostly what stays behind: stumps, roots, a mulch layer or bare soil. Two contractors can both say “we’ll clear it” and mean very different finished sites.

Method What happens What is left in the ground Usually suits
Brush clearing and mowing Cuts brush, vines and saplings near grade Root crowns, short stubs, cut material or shred Overgrown acreage, fence lines, fire breaks
Forestry mulching Grinds standing vegetation in place with a mulching head Stumps near grade, all roots, a mulch layer on the surface Pasture, trails, wooded yards, views, wildlife openings
Selective clearing Removes chosen trees and understory, protects keepers Depends on method used; keeper trees and their root zones Homesites in trees, park-like yards
Clearing and grubbing Fells and removes vegetation, then pulls stumps and roots Disturbed bare soil with holes and loosened topsoil Building pads, driveways, parking, anything that will be graded
Stump grinding Grinds a stump below grade Lateral roots and a pile of grindings Lawns, single stumps, mowable ground
Stump extraction Digs out the stump and root ball A hole to backfill, disturbed soil Footprints of slabs, pavement and utility trenches

Grubbing is the step people most often assume is included and is not. Mulching and stump grinding leave the root system in place. That is fine under grass and a disaster under a concrete slab, because the buried wood decays and the ground above it settles. The difference between clearing and grubbing is the single most important line in any scope.

Excavation is a third thing again. Cutting high spots, filling low ones, building a pad and compacting it is earthwork done by an excavation or grading contractor. Homestead Land Clearing does not offer grading, building pads or dirt work; those are handoffs to a separate trade.

Match the method to what the land will become

Start with the end use, because that decides how far below the surface the work has to go. The same wooded acre might need a mulcher for one owner and an excavator for another.

Pasture or hay ground. Mulching or shredding usually fits, with stumps left low enough to mow. Roots stay and hold the soil, but some species will come back from those roots, so a pasture plan needs follow-up. The pasture clearing page covers bush hogging and acreage mowing for this kind of ground.

A yard or open lawn. Mulching or selective clearing, then stump grinding where a mower has to pass. Mulch depth matters here: a thick layer slows grass establishment, so the scope should say whether mulch is spread thin, piled or hauled.

A house site. The footprint, driveway and any septic or utility runs need clearing and grubbing so organic material is out of the ground the builder will grade. Trees you want to keep need protection zones marked before the first machine moves. Clearing land to build a house covers how that handoff works.

A driveway or access road. Clear the corridor wider than the drive itself so shoulders, ditches and equipment can fit, and grub where base material will sit. Mulching a corridor makes it passable on foot or by truck, but it is not a road subgrade.

Parking, pads and commercial sites. Full clearing and grubbing under the paved area, with debris and erosion control planned. Civil plans, a tree survey and stormwater paperwork often come first; see commercial land clearing.

If you are not sure which bucket your property falls in, the land clearing method assessment asks the same questions a site walk would.

How the equipment choices fit together

Equipment follows the scope, not the other way round. Each machine is good at one relationship between vegetation and ground.

A forestry mulcher shreds standing trees and brush into chips where they stand, either as a dedicated tracked machine or a head on a skid steer or compact track loader. Tracks spread the load better than tires on soft clay, and a dedicated mulcher handles bigger trunks than a loader-mounted head. Either way, it cuts at or just above grade and pulls no roots.

A brush mower (a heavy rotary cutter, or bush hog) handles grass, weeds and saplings up to its rated size. It is the fast choice for overgrown pasture and the maintenance tool after a bigger clearing, and it does nothing below the surface.

An excavator is the stump and root tool: it digs out the stump and root ball, shakes the soil back into the hole and stacks the wood. It is slower per acre than a mulcher but leaves ground a grading contractor can work.

A dozer with a root rake pushes over trees and rakes roots and stumps into windrows across larger tracts. It moves a lot of material quickly, but it also moves topsoil, so it is a poor fit near trees you are keeping or where you want soil left in place. The forestry mulching vs land clearing guide compares the two approaches in depth.

A stump grinder chews a single stump below grade. It is the right answer for a lawn and the wrong one under a slab; stump grinding vs stump removal explains why.

Debris handling closes the loop. A grapple picks up logs and brush to stack, feed a chipper or load a dump truck for haul-off. Each step costs machine time, which is why “where does the wood go?” moves the price as much as the clearing.

Rock changes the plan too. USDA NRCS soil survey data lists shallow Eddy soils over chalk near Frisco, and hard ground wears mulcher teeth, limits stump height and slows grubbing.

What grows here, and what comes back after clearing

North Texas sits across two very different landscapes. Most of Collin County and eastern Denton County is Blackland Prairie, now largely farmed or developed, where clearing jobs tend to involve fencerow trees, creek-bottom woods and brush that took over idle fields. Western Denton County, around Aubrey and Pilot Point, is East Cross Timbers. Texas Parks and Wildlife Department describes those woodlands as dominated by post oak and blackjack oak with cedar elm and hickory, with eastern redcedar, mesquite, bois d’arc and greenbriar also common.

What happens after the cut depends on the species:

  • Eastern redcedar. Texas A&M AgriLife classes eastern redcedar as a non-resprouting juniper: once the main stem is cut or killed, it does not sprout back from the root collar. Cut it low, below the lowest green growth, and that tree is done. New cedars still arrive from seed that birds spread, so cleared ground needs watching for seedlings.
  • Mesquite. Texas A&M AgriLife describes mesquite’s belowground bud bank, which lets it survive disturbance and even fire. Cut or shred the top and it typically comes back with several stems. Mulching mesquite without a follow-up plan often produces a thicker clump than the single trunk you started with. AgriLife’s Brush Busters guidance says to let top-killed mesquite grow for two full growing seasons before using its leaf-spray method, and that mesquite control is not a one-time job.
  • Hackberry and most hardwoods. AgriLife’s Brush Busters program notes that most woody plants resprout profusely from belowground crowns or roots when the top is removed, and that cutting without treating the stump can make a woody plant problem worse. Expect hackberry to come back from a cut stump unless it is grubbed or treated.
  • Chinese privet. The City of Denton runs a removal initiative for privet, which forms dense thickets along fencerows, creeks and woodland understory. Treat it like the other resprouting shrubs: cutting alone is a start, not a finish.
  • Greenbriar and poison ivy. Both are vines that tangle in brush and fencelines. The CDC’s occupational safety institute (NIOSH) warns that smoke from burning poison ivy can irritate the lungs and advises against burning brush piles that may contain it, even where burning is legal.

So “will it grow back?” has a different answer for each plant on the property. Grubbing removes the root crowns that resprout; mulching does not. Without grubbing, plan follow-up: mowing, stump treatment by a licensed applicator, or grazing. The does brush grow back after clearing guide covers follow-up in detail, and North Texas invasive brush covers hackberry, privet and honey locust. If the property is a wall of vines, read poison ivy and greenbriar on overgrown acreage before anyone walks it in shorts.

Blackland clay, wet ground and when to schedule

The soil under most of this area is the biggest scheduling variable. USDA NRCS soil survey data shows Frisco and most Collin County towns dominated by Houston Black clay, with Austin and Stephen silty clays and Heiden clay nearby. Houston Black has a linear extensibility around 12 percent, which means it swells a great deal when wet and shrinks and cracks when dry. Wet, it is sticky and soft. Machines rut it, compact it and track it onto streets.

Western Denton County is different. Around Aubrey and Pilot Point the survey shows Cross Timbers sandy loams that drain well and shrink and swell far less, so they firm up faster after rain.

NOAA’s 1991 to 2020 normals at DFW Airport put annual rainfall at 37.01 inches, with peaks in May (4.78 inches) and October (4.37 inches). July and August are the driest months, around 2 inches each. On clay, that pattern means:

  • Spring and fall jobs carry the most weather risk. A soaking rain can push a start back several days while the ground firms up.
  • Midsummer ground is firm and easy on equipment but cracked, and bare soil left after clearing sits waiting for the next storm to wash it.
  • Dry late summers are when Collin and Denton counties have issued burn bans, which can take burning off the table exactly when the ground is best for machines.

Working wet clay is possible but costs more in slower production, rut repair and erosion control. Clearing wet clay ground covers the trade-offs, and how long land clearing takes covers what stretches a schedule.

Debris: mulch it, chip it, haul it or burn it

Every tree that comes down has to go somewhere, and the debris plan often decides the method. A quote should name one of four outcomes for each part of the site.

Mulch in place. The wood stays as a surface layer that shields soil from rain. No hauling or burning, but a poor fit where the ground will be built on.

Chip. A chipper reduces cut limbs and small trunks to chips that can be spread, piled for use or hauled more compactly. In Frisco, trees cut under a tree permit must be chipped and used as mulch on site or hauled off within 72 hours of cutting, according to the City’s tree code.

Haul off. Logs, stumps and brush go to a disposal site. North Texas Municipal Water District runs the regional system serving Frisco: its transfer stations charge $80 per ton and the 121 Regional Disposal Facility in Melissa $52 per ton, each with a one-ton minimum (North Texas Municipal Water District). Brush and limbs at the City of Plano’s Custer Road yard-waste facility, which Frisco shares, cost $22 per cubic yard with a $66 minimum. Stumps and root balls are not accepted at the curb in Frisco. Inside Frisco city limits, only the City’s contracted hauler may place a construction roll-off; the City of Frisco lists $357.95 per haul plus disposal by the ton, $108.87 delivery, $4.47 per day and a $1,000 deposit. The land clearing debris removal page covers hauling in more detail.

Burn. This is the option people expect and the one with the most conditions. Collin and Denton counties are in the Dallas-Fort Worth ozone nonattainment area, according to the Texas Commission on Environmental Quality. In those counties, TCEQ’s outdoor burning rule (30 TAC 111.209) allows burning land-clearing debris grown on the property only when no practical alternative to burning exists, and only under the conditions in 111.219. Those include staying at least 300 feet from off-site structures with people in them unless they agree in writing, starting no earlier than an hour after sunrise and finishing no later than an hour before sunset, attending the fire constantly, and not burning when forecast wind is under 6 or over 23 mph.

Local rules stack on top of TCEQ:

  • Frisco requires a burn permit from the fire code official, issued only to the landowner, with the burn at least 300 feet from any structure (City of Frisco Fire Prevention Office). A contractor cannot pull it for you.
  • Other cities differ sharply. Princeton does not allow burning to clear land at all. Celina issues burn permits at $100 per burn, only for parcels of 2 acres or more. McKinney sets its own burn distances through the Fire Marshal, so they are confirmed before any burn. The Princeton, Celina and McKinney pages carry each city’s details.
  • Unincorporated areas follow county practice. The Collin County Fire Marshal says no county office can authorize outdoor burning; only TCEQ’s exceptions apply. Denton County decides burn days each morning and requires registration before burning.
  • County burn bans are temporary Commissioners Court orders, usually issued in dry spells and renewed or lifted as conditions change. They can apply for weeks or months, and they override everything above. Check the current order before planning any burn.

Burning is never a given here. The burning brush in Collin and Denton County guide covers the rules in more depth.

Permits and rules to check before a machine shows up

The rules depend on the address: city or county, platted or not, whether a creek or lake touches it, and what runs under and over it. Checking them is step two of Homestead Land Clearing’s process, because a missed rule is the most expensive mistake in clearing.

Tree permits and mitigation

Frisco requires a Tree Removal Permit to remove any tree in the City regardless of size or species, except trees on a single-family or two-family lot within a plat of record (City of Frisco Code of Ordinances). Most clearing work, on acreage, unplatted land and commercial sites, falls inside that rule. A protected tree is a healthy tree 6 inches or larger in diameter at 4.5 feet that is not on the City’s excluded list, or any tree 4 inches or larger in the riparian buffer. Replacement scales with size: 0 percent for trees under 6 inches, 100 percent of the inches removed for 6 to 12 inches, 150 percent for 12.1 to 20 inches and 300 percent above 20 inches. Owners can plant on site, pay into the Tree Mitigation Fund at a per-inch value the City sets each year, or combine the two.

The Frisco process also controls timing. The tree survey, prepared by an arborist or a Texas-licensed landscape architect, has to be approved and the permit issued before clearing starts, and trees are checked in the field before grading or clearing proceeds. The Frisco tree removal permit guide walks through it step by step.

Texas law sets some limits on what cities can charge. Under Local Government Code 212.905, a city may not require a mitigation fee for a tree under 10 inches in diameter on an existing one- or two-family home that is the owner’s residence, and a city that charges mitigation fees must offer a credit for planting trees: 100 percent of the fee for planting at your own residence, at least 50 percent for residential development and at least 40 percent for non-residential (Texas Legislature).

Neighboring towns write their own rules, and they do not match Frisco:

  • Celina protects trees 6 inches and larger and requires a tree survey, or a note that no protected trees exist, before grading permits. Replacement runs 5:1 for oaks, pecan and any floodplain tree, 3:1 for elms, ash, pines, hickory and walnut, and 1:1 for hackberry, bois d’arc, cottonwood, cedars and mesquite.
  • McKinney issues a limited-purpose tree permit for selective thinning and for clearing underbrush with mechanical equipment.
  • Fairview prohibits clear-cutting and allows underbrush clearing under protected trees only by permit, by hand or with mowers.
  • Lucas requires a tree removal and site clearing permit before any protected tree comes out.
  • Prosper requires a tree permit for all trees except on platted single-family lots.

Unincorporated land in Collin County and Denton County generally has no city tree ordinance, but floodplain, stormwater and burn rules still apply.

Creeks, floodplain and Lewisville Lake

Creek bottoms are where clearing rules bite hardest. In Frisco, removing trees or other vegetation in the base floodplain or floodway, including by herbicide, requires a grading permit or a letter of approval from the City. Fines run $300 per caliper inch per tree and $300 per 100 square feet of vegetation, up to $2,000 per offense, and the contractor is subject to the same fines as the owner (City of Frisco Code of Ordinances).

Along Lewisville Lake, the U.S. Army Corps of Engineers generally owns land at or below elevation 535 feet, and its flowage easement extends to the 537-foot contour. Written Corps permission is required for any work within the flowage easement, and removing vegetation on public land is prohibited. Owners in Little Elm and Oak Point should confirm where their line sits before anything is cut. Pushing debris into a creek or drainage is never acceptable; it creates a flood hazard and the cleanup lands on the owner. See clearing near creeks and floodplain for the details.

Stormwater permits

TCEQ’s Construction General Permit (TXR150000) applies to soil-disturbing work such as clearing, grubbing and grading. Disturbing 1 to under 5 acres makes a small construction site; 5 acres or more makes a large site that files a Notice of Intent, with a fee of $225 filed electronically or $325 on paper (Texas Commission on Environmental Quality). Disturbance that is part of a larger common plan of development counts toward the total, so a 2-acre phase of a 10-acre plan is not a small site. A stormwater pollution prevention plan has to be in place before work begins. Frisco separately requires every owner to keep silt from leaving the property and can withhold permits and fine up to $500 per day. The stormwater permit for land clearing guide covers who files what.

Buried and overhead utilities

Texas law defines excavation as mechanized digging that disturbs soil 16 inches or deeper, and requires a call to Texas811 no earlier than 14 days and no later than 48 hours before the work, not counting weekends and holidays (Texas Utilities Code Chapter 251). Pulling stumps and grubbing roots easily reaches that depth. The same law warns that some water and sewer operators may not receive an 811 notice.

Frisco runs its own line locates separately from 811. The City locates its lines in right-of-way and easements for contractors holding an active right-of-way, TxDOT or irrigation permit when digging deeper than 18 inches, and it does not locate on private property (City of Frisco Public Works). Private lines, such as a feed to a barn or well, are on the owner to find.

Overhead lines are a separate hazard. Oncor tells customers not to go or bring materials within 10 feet of high-voltage lines and to contact Oncor to arrange the work. Trees touching lines are for the utility’s line-clearance crews, not a clearing contractor. Parts of the area are served by electric cooperatives instead of Oncor, so check whose poles they are. Clearing near utilities and power lines and who is responsible for clearing an easement go further, and the easement clearing page covers right-of-way work.

Ag valuation and rollback taxes

If your land is appraised as open-space agricultural land (often called 1-d-1 or “ag exemption”), clearing it for a house, a business or another non-agricultural use can count as a change of use. Under Texas Tax Code 23.55, a change of use triggers an additional tax equal to the difference between the taxes paid under ag valuation and the taxes at market value for each of the three preceding years (Texas Legislature). The chief appraiser decides whether a change of use happened, and the rule can apply to part of a parcel.

Clearing brush to restore pasture is a different situation from clearing for a building, but the appraisal district makes that call, not a contractor. Talk to the Collin Central Appraisal District or Denton Central Appraisal District, and a tax professional, before you clear land under ag valuation. The ag exemption and land clearing guide sets out the questions to ask; it is not tax advice.

Agricultural producers clearing brush for grazing can also ask USDA NRCS about its EQIP brush management practice, which ranks applications on a set date each fiscal year. It is a farm conservation program, not a homeowner rebate.

Timber value is uncommon here

Owners of wooded acreage sometimes hope timber will offset the clearing bill. In Collin and Denton counties that rarely works out. Texas A&M Forest Service tracks the state’s commercial timber harvest in a 43-county East Texas region, and research found no evidence that Collin or Denton is part of it or that local sawlog buyers operate here. Post oak, cedar elm, hackberry and mesquite in fencerow sizes are not what mills buy, and hauling to a distant mill eats any value. A large walnut or pecan can be an exception, but that takes a local evaluation. The can timber pay for land clearing guide explains what a buyer looks for. Homestead Land Clearing does not offer timber harvest.

Where clearing stops and excavation starts

Clearing ends when vegetation, stumps and roots are dealt with to the agreed finish. Excavation starts when soil itself is being moved to change the shape of the ground. A clearing contractor may smooth the surface it disturbed while grubbing, backfilling stump holes and leaving the site tidy, but that is not grading.

Building pads, cut and fill, compaction, rough and finish grading, leveling, pond digging, driveway base, concrete, retaining walls and drainage systems all belong to other trades.

Topsoil is the grey area. Grubbing disturbs it, and some sites strip it for later reuse. Who strips, where it is stockpiled and who spreads it back should be written into both contracts so it is not handled twice. The clearing land to build a house guide covers that handoff, and the lot clearing page describes the clearing side of a homesite.

Erosion control and stabilization after clearing

Vegetation is what holds bare soil in place. Remove it and the next heavy rain can carry clay into the street, a neighbor’s yard or a creek. On Blackland clay, where spring and fall storms land on ground with little cover, this happens fast.

The fix depends on what comes next:

  • Ground going back to grass or pasture. Seed promptly and leave mulch or grindings as cover where it will not smother the seed. Hydroseeding runs about $0.12 to $0.35 per square foot (HomeGuide, national); large TxDOT projects in North Texas see about $0.05 to $0.30.
  • Ground waiting for a builder. Silt fence along the downhill edges, a stabilized entrance so trucks do not track mud, and protection for any storm inlets. On TxDOT projects in the Dallas district, silt fence runs about $3.50 to $5 per linear foot installed and about $1 per foot to remove; short runs on one lot can cost more per foot.
  • Slopes and creek banks. Keep vegetation where possible and treat cleared slopes first. Clearing a slope does not change its grade; it only removes what was holding it.

Homestead Land Clearing offers silt fence and seeding as add-ons. The erosion control after land clearing guide covers timing and materials.

Urgent, or can it wait?

Most clearing is planned work. A few situations move faster.

Act soon:

  • A Frisco code enforcement notice. The City’s rule is that ground vegetation cannot exceed 12 inches, and limbs cannot block sidewalks, alleys or drivers’ sightlines. The overgrown lot clearing page covers this kind of job.
  • A tree or limb on or against a power line. Call the electric utility, not a clearing contractor.
  • Storm-downed trees blocking access or a drainage path.
  • Brush stacked against a house or barn in dry weather. The fire breaks around rural homes post covers defensible space.

Plan it:

  • Clearing for a future build, where tree permits, surveys and stormwater plans set the pace.
  • Pasture reclamation, which is often better timed for firm ground and the growing season.
  • Clearing a lot you are buying, inheriting or managing from out of town; the inherited or absentee lot post covers that case.

How to compare land clearing quotes

Homeowners report that verbal quotes are where most clearing disputes start: a price agreed on a handshake, then a bill for twice as much, or a “cleared” lot with live trees cut that were meant to stay and brush pushed into a corner. The fix is a written scope that makes two quotes comparable.

Homestead Land Clearing’s process puts this in order: walk the property (boundaries, keeper trees, slopes, wet spots, fences, anything buried or overhead), check the rules for that address, write the scope in writing before a price, then clear to the agreed finish and hand off to the next trade or to seeding. Whoever you hire, a quote should answer each of these:

  • Area and boundaries. Acres or a sketched area, with property lines and limits marked on the ground.
  • Keeper trees. Which trees stay, flagged on site, and how their root zones are protected.
  • Method. Mulching, cutting, grubbing or a mix, and where each applies.
  • Stumps. Left at a stated height, ground below grade, or extracted, and where.
  • Roots. Left in place or grubbed, and to what area.
  • Debris. Mulched in place, chipped, hauled (to where) or burned (under whose permit).
  • Finish level. Rough cleared, mowable, seeded, or ready for the grading contractor.
  • Erosion control. Whether silt fence, seeding or other controls are included.
  • Hazards. Old fence wire, dumped debris, wells, septic and utilities, and how they are handled.
  • Changes. How extra work is priced and approved in writing before it happens.

The what a land clearing quote should include guide expands each line, and the printable scope checklist on the resources page is the same list in a form you can carry on a site walk.

What drives the price

Per-acre pricing tracks density more than anything else. As budgeting ranges, land clearing runs light $1,200 to $2,500, moderate $2,500 to $4,500 and heavy/wooded $4,500 to $8,000 per acre (HomeGuide, national). North Texas pricing we reviewed falls in the same range. Forestry mulching runs $500 to $1,000 or more per acre, or $125 to $300 per hour with operator (HomeGuide, national), and North Texas quotes commonly run higher than the national figure. These are ranges for planning, not anyone’s rates.

What moves a specific job within or beyond those ranges:

  • Density and trunk size. Thick cedar or mature hardwoods take far longer per acre than scattered brush.
  • Stumps and roots. Grubbing and extraction add excavator time and holes to backfill.
  • Debris plan. Mulching in place avoids hauling; haul-off adds loading, trucking and tipping fees.
  • Ground and access. Wet clay, slopes, rock, narrow gates and buried fence wire slow work and add repairs.
  • Protection work. Keeper trees, fences and utilities near the work need slower, careful passes.
  • Permits and controls. Tree surveys, mitigation, silt fence and seeding are real line items.
  • Mobilization. Hauling a large machine on a lowboy costs the same whether the job is half an acre or ten.

That last item is why small jobs feel expensive. Homeowners report that many operators quote a day rate or a minimum charge, so a quarter-acre of brush may cost close to a full day. Combining small tasks, such as a fence line plus a few stumps, can make a visit worth more for the same mobilization. The land clearing cost per acre guide has full tables, and the land clearing cost estimator gives a budgeting range from acreage and density.

Care after clearing

Cleared land does not stay cleared on its own. Plan on these in the first two growing seasons:

  • Mow the regrowth. A brush mower pass once or twice a year keeps sprouts from mesquite, hackberry and privet from getting ahead. On pasture, this is the cheapest follow-up there is; the fence line clearing page covers keeping perimeters open.
  • Watch for seedlings. Cedar and privet arrive from seed even where no stump resprouts; mow or pull them while small.
  • Get cover on bare ground. Seed, mulch or both, especially before May and October rains.
  • Check stump holes and soft spots. Backfilled holes can settle after the first wet season.
  • Keep the paperwork. Tree permits, mitigation records and the written scope matter when you sell or build.

For broader brush work on acreage, the brush clearing page covers cedar and mesquite specifically.

Start with what the land is for

The best clearing jobs start with a clear answer to one question: what will this ground be used for in a year? With that, the method, the debris plan, the permits and the price all follow. If you have a lot, acreage or a commercial site in Frisco, Collin County or Denton County, contact Homestead Land Clearing with the address, a rough size and what you want the land to become. We’ll walk the property, check the rules for that address and put the scope in writing before any price, so you know exactly what will be left in the ground when the work is done. Browse all land clearing guides or the service areas if you want to read more first.

Ask about your property

Tell us where it is and what it should look like after; a ZIP code is enough to start.

Step 1 of 2: the job

Questions people ask

Does clearing land raise what the property is worth?

It depends on the buyer and the end use, so nobody can promise it. Opening a lot for a house site or reclaiming pasture can make land easier to use and show, while mature shade trees are often valued by home buyers. Ask a local appraiser or real estate agent before clearing for resale, and clear selectively if you are unsure.

How do I find out whether a burn ban is in effect?

County burn bans are temporary orders from the Commissioners Court, so status changes. Check the current order on the Collin or Denton County website, the Texas A&M Forest Service burn ban map, and, in unincorporated Denton County, the Fire Marshal's daily burn-day determination. Cities also run their own burn permits and some ban land-clearing burns outright.

Will a land clearing quote include grading or a building pad?

Usually not. Clearing removes vegetation, and grubbing removes stumps and roots, but cutting, filling, leveling and compacting a pad is excavation and grading work by a separate trade. A good clearing scope says where clearing ends so the grading contractor can pick up without paying to redo anything.

More guides